Observation - 201928018 Audit Trail    << HEART Home  
What Next...

You can take the following actions on this observation:

Back
Originator:
Date Created:
21-Oct-2019
Business Unit:
TCS
Business Group:
Mining & Minerals
Project/Office:
Kemerton Project
Service Line:
APAC
Site/Office Name:
Kemerton Project Site
Work Related or Non-Work Related Observation?:
Work Related
Exact Location or Project of Act/Condition/Safe Behaviour:
SMP tank assembly area
Observation Type:
Safe Behaviour
Observer Name:
 Stephen Andrews
Observer Email Address:
steve.andrews3@woodplc.com
Originator Status:
Wood
Stakeholder:
Contractor
Observation Date:
17-Oct-2019
Observation Time:
10:30
Observation Close Date:
21-Oct-2019
Observation Category:
Job Factors
    Safety critical communications
Name of Individual or Team:
Civmec SMP
Details of safety observation:
Observed group removing tank from staging area and tracking to laydown area, very good communication between group , team talk before lift so all reading of the same page all appropriate paper work in place lift carried out without incident a good team effort
Immediate action taken:
Congratulated team of first major lift for SMP, and keep up the standard
Supporting Information:
Feedback required?:
No

      